Thursday, June 24, 2010


This is my board completley wired and tested. All the test results were satisfactory and the installation is safe to liven.

The rest of the switchboard was quick to to finish wiring. My incoming cables from the meter panel are suppost to be 16mm2 for the phase and neutral and 2.5mm2 for the pilot. There was no 16mm2 cable left so I had to use 4mm2 whch was the largest available size.

I have made my panel live and finished the live testing. The RCD's were working and my sub-circuits all had satisfactory test results.

This installation is fully operational and safe to use.